- NEOM Company
- SAR 114,168,000
- April 30, 2024
- September 30, 2024
Scope of Work:
Transportation, removal, and stockpiling of excavated materials
Project Data Highlights
Total Haulage Material
4,500,000 M3
Total Number of Trucks
400
Total Number of Equipment
100 Equipment
Work Time
2 Shifts Day/Night
Total Number of Manpower
600 Monthly
Project Duration
3 Months