- Ministry of Transport and Logistics Services
- SAR 84,999,999
- July 16, 2012
- August 27, 2021
Scope of Work:
Construction and execution of the completion of the Al-Ula / Al-Hijr dual road over a length of 15.45 km, the completion of the Al-Jadidah road over a length of 20 km, and the completion of the Al-Qarm / Al-Farsh road over a length of 15 km.
Project Data Highlights
Number of Links
5
Total length of Links
33.7 KM
Total Quantity of Cuts
401,794 M3
Total Quantity of Fills
1,168,009 M3
Total Quantity of Asphalt
37,148 M3
Total Quantity of Concrete
5,000 M3
Total Quantity of Steel
997 Ton
Total Quantity of Road Paint
25,620 M2
Total Number of Cat Eyes
13,475 Pcs
Total Quantity of Road Signboard
741 M2