- Ministry of Transport and Logistics
- SAR 147,870,956
- July 6th, 2011
- June 22nd, 2016
Scope of Work:
A 6 km-long highway consisting of four lanes in each direction, including the construction of an intersection, ramps, drainage structures, and safety measures.
Project Data Highlights (Phases 1/5)
Number of Links
5
Total length of Links
28,83 KM
Total Quantity of Cuts
4,568,269 M3
Total Quantity of Fills
4,400,273 M3
Total Quantity of Asphalt
256,860 M3
Total Quantity of Concrete
56,390 M3
Total Quantity of Steel
5,191 Ton
Total Quantity of Road Paint
29,596 M2
Total Number of Cat Eyes
16,000 Pcs
Total Quantity of Road Signboard
350 M2
More Projects
How Does Al Mardoof Ensure Client Success?
Our client-focused approach ensures every project meets their goals, budgets, and timelines.