- NEOM Company
- SAR156,275,000
- 07/12/2023
- 30/09/2024
Scope of Work:
Transportation, relocation, and stockpiling of excavation materials.
Project Data Highlights
Total Haulage Material
10,250,000 M3
Total Number of Trucks
750
Total Number of Equipment
120 pieces of equipment
Work Time
2 Shifts Day/Night
Total Number of Manpower
1200 Monthly
Project Duration
4 Months