Work Order No. 4200000128.002 – THE LINE – Stockpile Management – SP3


  • NEOM Company

  • SAR156,275,000

  • 07/12/2023

  • 30/09/2024


Scope of Work:

Transportation, relocation, and stockpiling of excavation materials.
Al Mardoof earthworks machinery in Madinah

Project Data Highlights

Total Haulage Material
10,250,000 M3
Total Number of Trucks
750
Total Number of Equipment

120 pieces of equipment

Work Time
2 Shifts Day/Night
Total Number of Manpower
1200 Monthly
Project Duration

4 Months