- Ministry of Transport and Logistics
- SAR 111,529,970
- 21/ July /2008
- 17/ October /2017
Scope of Work:
- Construction of Directional Ramp No. 1 from Al Madinah towards Hail, with a length of 5.231 km
- Construction of Directional Ramp No. 2 from Hail towards Al Madinah, with a length of 7.238 km
- Construction of the valley bridge on Ramp No. 2, along with the intersection.
Project Data Highlights (Phases 1/5)
Number of Links
5
Total length of Links
28,83 KM
Total Quantity of Cuts
4,568,269 M3
Total Quantity of Fills
4,400,273 M3
Total Quantity of Asphalt
256,860 M3
Total Quantity of Concrete
56,390 M3
Total Quantity of Steel
5,191 Ton
Total Quantity of Road Paint
29,596 M2
Total Number of Cat Eyes
16,000 Pcs
Total Quantity of Road Signboard
350 M2